Uisge Dubh

The Uisge Dubh Hydro Project is a 2MW scheme located near the village of Strathcarron, Wester Ross in the Western Scottish Highlands.

A 1.8km pipe transfers water from two intakes to the powerhouse. This vertical drop, known as the 'Gross Head' of the project is 85m. The pipeline is made of Glass Fibre Reinforced Plastic (GRP) and High Performance Polyethylene (HPPE). A Gilkes Francis solution is used, operating at a design flow of 3,020 l/s. This turbine is a reaction type turbine which is optimised for low-head, high-flow applications and provides high efficiency at peak power.

Construction mobilization started in May 2016. As well as being an investment partner in the project, Gilkes Energy is also the lead engineer, providing design, project management and construction supervision services during the construction phase, as well as managing the operation and maintenance of the facility thereafter.
 
The project started generating in September 2017 and was delivered on time and on budget.
 
See photographs above of both the construction phase and the finished project.
 